It has been another busy week on the St. Albans State Office Building and City Parking Garage job site. Superintendent Steve Rowe writes that drywall taping is underway on the 2nd floor and that 40% of the drywall on the 3rd floor is now installed. The north brick wall is complete and the west wall is in progress. The connector ramp concrete slab has been poured and the mechanical, electrical, and plumbing subs are all fully engaged.

Superintendent Jim Hoag submitted photos this morning showing the crane being disassembled and trucked off to its next job!